IH 30 “The Canyon” from IH 35E to IH 45 / IH 345 – TxDOT Dallas District

 

About this Project

EST provided design services for this project, the purpose of which is to reconstruct and widen IH 30 “The Canyon” from an 8-lane urban to a 12-lane urban divided depressed interstate from IH 35E to IH 45/IH 345 in Dallas County.

The EST team performed:

  • Performed geotechnical investigations including soil borings, piezometers installation, monitoring, and abandonment, pavement coring, and all associated material testing,
  • Provided geotechnical data along with WINCORE logs for use in bridge/retaining wall foundation design,
  • Provided Field Survey data,
  • Designed Retaining Walls RW201-RW210,
  • Designed Removal Plans, Roadway Plans, and provided Traffic Control plan design support, and
  • Performed Constructability Review.

Key Challenges: Development Schedule. Project Kick-Off held Sept. 24, 2020 with the first plans submittal (for walls and bridges) scheduled for January 28, 2021. EST staff used 3D design technology to deliver preliminary retaining wall designs to the Client 2-weeks early

Services provided

  • 3D Retaining Wall Design
  • Roadway Design
  • Sequence of Construction Coordination
  • Geotechnical Investigations, Material Testing, Design and Reporting
  • Design Survey

Estimated Construction Costs: $362.5 Million

Completion Date: In Progress – Scheduled for December 2023

Project Owner – TxDOT Dallas District

Prime Consultant – WSP USA, Inc.

Project Reference – Fernando Cruz, P.E. – Deputy Project Manager

EST Sub Consultant – Kelly Selman, P.E. 

Project Photos

Check out all of our past projects for our varying services!

Contact Us

615 N Hudson Avenue, Suite 300 Oklahoma City, OK 73102

(405) 815-3600

(405) 815-4080

EST has been aquired by WSB. Click here.