The project is currently 37% complete
- Project Length = 5 miles
- New road construction
- This project connects US-412 to I-44 as part of the Western loop around the Tulsa metro area.
- The project involves a funding partnership between the Oklahoma Turnpike Authority, City of Tulsa, Tulsa County, Indian Nations Council of Governments, Oklahoma Department of Transportation and FHWA.
- Anticipated completion is Fall of 2022.
- Notice: 31st Street S. is closed between S. 57th W. Ave. and S. 54th W. Ave. through December 31, 2020, to allow for roadway construction activities in this area.
- Notice: 57th W. Ave will be closed through Nov. 24th, between W. 21st Street South and W. 22nd Street S. for construction of a drainage structure which will pass under S. 57th W. Ave.
- Notice: 51st Street S. has been detoured onto temporary pavement for a period of approximately one year to allow for the construction of the new W. 51st Street S. roadway and bridge.
Construction of the substructure of the new bridge at W. 31st Street S. continues.
57th W. Ave will be closed through Nov. 24th, between W. 21st Street South and W. 22nd Street S. for construction of a drainage structure which will pass under S. 57th W. Ave.
Construction of the new Arkansas River bridges continues